Tuesday 10 June, 2025
Replacement of the elevators in building 3B weeks 32-41
The elevators in building 3B will be replaced.Lift 1: week 32-36Lift 2: week 36-41Work should be planned so that jobs that cause structure-borne noise are done when it is least disruptive.The first week (weeks 32 and 37) is demolition where there is sawing with a reciprocating saw, and some running in the corridor with demolition material.The second week (week 33 and week 38) involves the installation of guides in the shaft with structural noise for approximately 2 hours in the morning.The third and fourth weeks (weeks 34-35 and weeks 39-40) are mostly montages where some montages with body sounds may occur in the mornings.Fifth week (weeks 36 and 41) is commissioning, programming and inspection